240 MWh battery storage project financed at 78% debt without a corporate guarantee
An early-stage storage developer with a strong site, a weak balance sheet, and a $94M build to fund. We built the project-finance package, ran the lender process, and reached NTP without putting the parent on the hook.

- $94M project cost against $21M of developer equity capacity, 78% leverage required to make IRR work.
- No corporate guarantee available, parent balance sheet too thin to credibly underwrite one.
- Revenue stack mixing capacity payments, ancillary services, and merchant arbitrage, lender models could not price all three.
- Battery degradation curves disputed between the OEM, the developer's engineers, and the lender's technical advisor.
- EPC fixed-price wrap not yet signed at start of lender outreach.
Revenue stack modeling
Built a probabilistic revenue model across capacity, ancillary, and merchant tranches with a 1,000-iteration Monte Carlo. P50, P90, and P99 cases handed to lenders with full assumption visibility.
Degradation negotiation
Brokered a three-party warranty schedule between OEM, developer, and lender technical advisor, locking residual capacity at year 10 and year 15.
EPC wrap & contingency
Negotiated EPC fixed-price wrap with liquidated damages, then layered a 6% contingency reserve to satisfy the lender base case.
Lender process
Ran a structured RFP across 6 project-finance banks. Drove three to firm term sheets at 75% or higher leverage; selected the lead on covenant package, not headline rate.
A Northern European battery storage developer holding a 240 MWh permitted site with grid connection secured. Total project cost $94M, internal equity capacity $21M, and a developer balance sheet too thin to support a corporate guarantee. The team had been quoted 60–65% debt by two banks demanding a parent guarantee they could not provide. Project IRR penciled at 14.3% unlevered, but only if leverage cleared 75%.
- Month 1
Diagnostic & financial model
Project model rebuilt with probabilistic revenue stack. Equity IRR triangulated against required leverage.
- Month 2
Degradation & EPC
Three-party warranty schedule agreed. EPC fixed-price wrap signed with LDs and 6% contingency.
- Month 3
Lender outreach
6-bank RFP launched. NDAs and data room access live in week 9.
- Month 4–5
Term sheets
Three firm term sheets received at 75%, 77%, and 78% leverage. Selected the 78% offer on covenant flexibility.
- Month 6
Documentation
Common terms agreement, intercreditor, and direct agreements negotiated. Independent engineer signed off.
- Month 7
FID & NTP
Final investment decision reached. Notice to proceed issued to EPC. First drawdown completed.
- $73M of senior project-finance debt closed at 78% leverage, no parent guarantee.
- Equity IRR re-rated from 11.2% to 18.6% on the new capital stack.
- NTP issued 7 months from FID, two months ahead of the developer's internal plan.
- Project template adopted by the developer for two follow-on sites already in permitting.
- Lender relationship now anchored for the developer's next three projects.
- 01
Probabilistic revenue modeling is the difference between 60% leverage and 78% on a hybrid revenue stack.
- 02
Lender selection on covenant flexibility beats headline rate every time on a developer's first large project.
- 03
EPC wrap plus contingency reserve is the single fastest path to lender base case acceptance.
"Two banks told us we needed a corporate guarantee we couldn't sign. CapMaven built the model that proved we didn't, and then ran a process that got three banks competing for the deal."
How does this work for developers without a permitted site?+
It doesn't, yet. We come in at FID or 90 days before. Pre-permit financing is a different exercise: development capital, not project finance.
Did the lender require an offtake contract?+
Two of the three bidders did. The selected lender accepted the probabilistic revenue stack with a P90 floor mechanism in lieu of a fixed offtake, which preserved merchant upside.
Can the same structure work for solar or wind?+
Yes, but the revenue stack is simpler (PPA-heavy) and the leverage ceiling is higher already. The differentiator on storage is the merchant component, which is where modeling work earns its return.
Your case starts here.
Two weeks. Three scenarios. One honest read on your numbers.
The CFO Diagnostic gives you the same artifact every case above started with, a cash model, a unit-economics teardown, and a capital-readiness scorecard.
Start here,
Stop guessing. Start knowing.
Book a free 20-minute discovery call, or go straight to a $400 CFO Diagnostic. The Diagnostic delivers a working read of your cash position, runway, and top 3 financial risks within two weeks. Whether you engage further or not, it's the clearest financial picture most founders have ever seen.
